1. Executive Summary 执行摘要

BDIC is a 500 MW green hyperscale AI data centre campus in Bogor, West Java, positioned as Southeast Asia's first at-scale, power-secured, renewable-led, AI-native infrastructure play. ByteDance is the keystone anchor. BDIC 是位于印尼西爪哇茂物的 500 兆瓦绿色超大规模 AI 数据中心园区,定位为东南亚首个规模化、电力锁定、可再生能源主导、AI 原生的基础设施标的。ByteDance 为基石锚户。

Land Area
土地面积
181 ha
Single contiguous parcel · rare in Java单一连片地块 · 在爪哇极为罕见
Phase 1
一期规模
100 MW
USD 820-900M · Month 30-36 COD8.2-9.0 亿美元 · 第 30-36 个月投运
Blended Power
混合电价
$0.062/kWh
vs Singapore $0.12-0.16 · 2× advantage相较新加坡 0.12-0.16 美元 · 两倍成本优势
Tax Holiday
税收假期
20 years
PMK 69/2024 · pioneering industry依据 PMK 69/2024 号法规 · 先导产业认定

Highlights 核心亮点

  • Power de-risked from Day-1 — >80% renewable PPAs (geothermal + solar) signed pre-FID; blended cost 2× cheaper than Singapore电力自投运首日起即已去风险——超过 80% 的可再生能源购电协议(地热 + 光伏)在 FID 前签署;综合电价较新加坡便宜一半。
  • Anchor secured — ByteDance 30-80 MW initial, ramping to 150-250 MW strategic scale under a 10-year BTS lease锚定客户已落实——字节跳动初期 30-80 MW,并按 10 年期定制建造(BTS)租约爬坡至 150-250 MW 的战略规模。
  • Infrastructure-grade returns — Project IRR 15-22% (unlevered), MOIC 2.0-3.2×, EBITDA margin 55-65%基础设施级回报——项目 IRR 15-22%(无杠杆口径),投资回报倍数 2.0-3.2 倍,EBITDA 利润率 55-65%。
  • Bankable structure — 65% senior debt from DFIs (IFC / ADB / AIIB), 35% equity, HoldCo SG/HK可融资的交易结构——65% 优先债来自开发性金融机构(IFC/ADB/AIIB),35% 股权,控股公司设于新加坡或香港。
  • Government tailwind — 20-year CIT holiday, OSS-RBA fast-track, KEK Nongsa Digital Park playbook, JFT facilitation政策顺风——20 年企业所得税免税期、OSS-RBA 审批快速通道、可复制 KEK Nongsa 数字园区的成熟路径、联合协调小组(JFT)保驾护航。
  • First-mover moat — Zero comparable 500 MW hyperscale campus exists in Java today先发护城河——爪哇岛目前尚无任何可与之对标的 500 MW 级超大规模园区。

2. Investment Thesis 投资逻辑

Four structural forces converge at BDIC — making this the defining AI infrastructure bet in Southeast Asia. 四大结构性力量在 BDIC 汇合,使之成为东南亚 AI 基础设施的标杆性押注。

01

Demand Is Irreversible 需求不可逆

  • ByteDance anchor: 30-80 MW initial, 150-250 MW strategic scale字节跳动锚定:初期 30-80 MW,战略规模 150-250 MW
  • AI training & inference exploding across SEA — no comparable supply东南亚 AI 训练与推理需求爆发,供给端却无同量级产品
  • Indonesia data localisation law (PDP) forces in-country build印尼数据本地化法(PDP)倒逼云厂商在境内自建
  • Google, Alibaba Cloud, AWS actively seeking SEA expansion nodes谷歌、阿里云、AWS 均在积极物色东南亚扩张节点
02

Power De-Risked From Day-1 Day-1 电力去风险

  • >80% renewable PPAs signed before FID — geothermal + solarFID 前已签署超 80% 的可再生能源购电协议——地热 + 光伏
  • Blended energy cost ~$0.062/kWh vs Singapore $0.12-0.16/kWh综合能源成本约 0.062 美元/kWh,新加坡为 0.12-0.16 美元/kWh
  • Multi-point 150 kV PLN grid intake; 30 MW BESS ramp buffer150 kV 电网多点接入;配置 30 MW 储能作为爬坡缓冲
  • No power queue — unlike Singapore, Frankfurt, Northern Virginia不存在电力排队问题——这与新加坡、法兰克福、北弗吉尼亚形成鲜明对比
03

Infrastructure-Grade Returns 基础设施级回报

  • BTS leases: 10-15 year anchor terms, USD $110-140/kW/month定制建造租约:锚定客户 10-15 年租期,租金 110-140 美元/kW/月
  • CAPEX USD 7.5-8.5M/MW ex-land; project-financed 65% debt不含地价的单位造价 750-850 万美元/MW;项目融资中债务占 65%
  • CIT Holiday under PMK 69/2024 (up to 20 years)依据 PMK 69/2024 号法规可享企业所得税免税期(最长 20 年)
  • Total platform USD 4.0-4.4B; Phase 1 USD 820-900M平台总投资 40-44 亿美元;一期 8.2-9.0 亿美元
04

Structurally Defensible Moat 结构性护城河

  • 181 ha land in SPV — largest permitted hyperscale plot in Java181 公顷土地注入项目公司——爪哇岛已获批的最大超大规模数据中心地块
  • Tier III+/IV availability, PUE 1.15-1.20, liquid-first AI coolingTier III+/IV 级可用性,PUE 1.15-1.20,以液冷为主的 AI 散热方案
  • Carrier-neutral connectivity; metro fibre + SKKL wavelengths运营商中立的网络接入;城域光纤 + 海缆波长资源
  • Government-backed JFT facilitation; KEK Nongsa playbook政府背书的联合协调小组支持;可复制 KEK Nongsa 园区的成熟经验

3. Market Opportunity 市场机会

Southeast Asia is the world's fastest-growing data centre market — and Indonesia is the epicentre. 东南亚是全球增速最快的数据中心市场——印尼是其震中。

SEA DC Market by 2030
2030 年东南亚 DC 市场
$23B+
Indonesia Share of SEA DC Demand
印尼占东南亚 DC 需求
~35%
Indonesian Internet Users
印尼互联网用户
280M+
500 MW Hyperscale Campuses in Java Today
爪哇现有 500MW 级园区
Zero

Why Indonesia — Why Now 为什么是印尼、为什么是现在

Driver驱动因素Impact影响
Digital Sovereignty 数字主权PDP Law No. 27/2022 mandates local data storage for Indonesian users — hyperscalers must build in-country.第 27/2022 号《个人数据保护法》强制要求印尼用户数据存储于境内——云厂商别无选择,只能在本地建设。
AI Compute Deficit AI 算力短缺Regional AI clusters (ByteDance, Alibaba, Google) are supply-constrained; Singapore is power-gated, Johor filling fast.区域内 AI 算力集群(字节跳动、阿里、谷歌)普遍受制于供给;新加坡受电力配额限制,柔佛的可用容量正在被迅速填满。
Unbeatable Power Cost 无可匹敌的电价Blended $0.062/kWh renewable vs $0.12-0.16/kWh in Singapore — 2× cost advantage in the highest OPEX line item.可再生能源综合电价 0.062 美元/kWh,而新加坡为 0.12-0.16 美元/kWh——在运营成本占比最高的科目上形成两倍成本优势。
Government Tailwind 政府顺风President Prabowo's 'Digital Indonesia' agenda; 20-year CIT holiday; OSS-RBA fast-track; Joint Facilitation Team.普拉博沃总统的"数字印尼"国家议程;20 年企业所得税免税期;OSS-RBA 审批快速通道;政府联合协调小组。
300M Consumer Base 3 亿消费者基数275M population, 57% internet penetration growing to 80%+ — latency-sensitive AI inference demands local compute.2.75 亿人口,互联网渗透率 57% 并将升至 80% 以上——对时延敏感的 AI 推理业务必须依托本地算力。

4. Project at a Glance 项目一览

Ultimate IT Load
终期 IT 负载
500 MW
Gross Land Area
总用地面积
181 ha
First Energisation
首期投运
100 MW
Phase 1
Phase 1 CAPEX
一期资本支出
$820-900M
Renewable Day-1
Day-1 可再生占比
>80%
Campus PUE
园区 PUE
1.15-1.20
Per-Rack Density
机柜功率密度
30-80 kW
Anchor Lease Term
锚户租期
10-15 yr

5. Site & Location — Bogor, West Java 选址与场地

Location 位置Mulyaharja / Palasari / Pamoyanan, South Bogor南茂物 Mulyaharja/Palasari/Pamoyanan 一带
Gross Area 总面积~181 ha (447 acres)约 181 公顷(447 英亩)
Net Campus 园区净用地~125 ha — data halls, power, cooling, roads约 125 公顷——含机房、电力、冷却设施及道路
Buffer Zone 缓冲带~56 ha — green belt, stormwater, resilience约 56 公顷——绿化带、雨洪调蓄及韧性空间
Distance from Jakarta 距雅加达~60 km via Jagorawi Toll; 45 min drive经 Jagorawi 高速约 60 公里,车程 45 分钟
Elevation 海拔~300-350 m ASL — cooler ambient temps海拔约 300-350 米——环境温度更低,利于散热
Seismic 抗震SNI 1726 compliant; IFC EHS standards符合印尼 SNI 1726 抗震规范及 IFC 环境健康安全标准
Grid Access 电网接入GI Sentul / GI Bogor Baru / GI Cibinong (5-15 km)GI Sentul/GI Bogor Baru/GI Cibinong 三座变电站,距场地 5-15 公里
Water 水源Ciawi / Cisadane catchment; WUE < 0.2 L/kWh取自 Ciawi/Cisadane 流域;水资源利用效率低于 0.2 L/kWh
Bogor Inner Ring Road (BIRR) provides direct arterial access. Elevated inland site avoids Jakarta subsidence risk entirely. 茂物内环 (BIRR) 直接干道通达;高地内陆场地完全规避雅加达地面沉降风险。

Campus Zone Allocation 园区功能分区

Zone功能区Share占比
Data Hall Zones (AI + HPC)数据机房区(AI + HPC)45-50%
Power Infrastructure (HV/MV, BESS)电力基础设施(高压/中压、储能)10-15%
Cooling Systems (CDU / CT / CRAC)冷却系统10-15%
Green Belt & Stormwater绿化带与雨水管理15-20%
Roads, O&M, Connectivity PoPs道路、运维、连接节点~10%

6. Phased Development — 100 → 500 MW 分期开发路线图

Capital-efficient, demand-anchored phasing — each phase triggers the next. No speculative build. 资本高效、以需求为锚的分期节奏——每一期触发下一期,无投机性建设。

Phase 1 · Years 1-3
100 MW
USD 820-900M
  • Anchor hall: ByteDance 30-80 MW锚定机房:字节跳动 30-80 MW
  • HV grid 150 kV, 2× GI feeds150 kV 高压电网,双变电站进线
  • BESS 30 MW / 160 MWh储能系统 30 MW/160 MWh
  • Solar + geothermal PPAs >80% renewable光伏 + 地热购电协议,可再生占比超 80%
  • Carrier-neutral PoP + dark fibre运营商中立接入点 + 裸光纤
  • Tier III+ / hybrid Tier IVTier III+ 级,局部达 Tier IV 混合标准
Phase 2 · Years 3-5
+150 MW
USD 1.1-1.3B incremental
  • Scale ByteDance + Alibaba/Google/AWS字节跳动扩容,并引入阿里/谷歌/AWS
  • Additional HV intake (multi-point)增设高压进线(多点接入)
  • Expand BESS to 75-100 MW储能扩容至 75-100 MW
  • Full liquid-cooling build-out液冷系统全面铺开
  • Floating solar PPAs (200-300 MWp)水面光伏购电协议(200-300 MWp)
  • Near-100% renewable matching可再生能源匹配率接近 100%
Phase 3 · Years 5-10
+250 MW
USD 2.0-2.2B incremental
  • 500 MW campus fully energised500 MW 园区全部投运
  • 800V HVDC-ready distribution配电系统支持 800V 高压直流
  • BESS 200+ MW / 1 GWh campus total园区储能合计 200 MW 以上/1 GWh
  • CLS subsea cable participation参与海缆登陆站建设
  • Potential IPO / REIT exit optionality保留 IPO/REIT 退出的可选路径
  • Full 24/7 renewable matching实现 7×24 小时全时段可再生能源匹配

7. Power Architecture & Green Energy 电力架构与绿色能源

Grid-hardened. Renewable-first. Bankable. PPA-led portfolio: ground solar + geothermal backbone, BESS-enabled, scalable to 100% over time. 电网加固,可再生优先,可银团化融资。以 PPA 为主导:地面光伏 + 地热基荷,BESS 使能,可逐步扩至 100%。

Energy Portfolio 能源组合

Source来源Share占比Cost (¢/kWh)电价Role角色
Ground Solar (PPA)地面光伏35-40%4.5-6.5¢Lowest LCOE, fastest COD度电成本最低,投运最快
Geothermal (PPA)地热30-35%8.0-9.5¢Firm clean baseload稳定可靠的清洁基荷电源
Floating Solar (PPA)水面漂浮光伏10-15%5.5-7.5¢Scale without land risk规模化扩张且不占用土地、无征地风险
PLN Grid + RECsPLN 电网 + 绿证10-15%7.0-9.0¢Balancing / bridge用于平衡调节与过渡衔接
BESS (30 MW / 160 MWh)储能电池系统Enables使能环节Ramp smoothing, firming平滑爬坡、提升出力可靠性
Blended energy cost ~$0.062/kWh vs SGD $0.12-0.16/kWh in Singapore. PLN Grid: 150 kV Java-Bali Transmission · Candidates: GI Sentul, GI Bogor Baru, GI Cibinong (5-15 km) · Multi-point HV intake for N+1 resiliency · Phase 1 power contract targeted pre-FID. 综合能源成本约 0.062 美元/kWh,而新加坡为 0.12-0.16 美元/kWh。电网侧:接入 PLN 150 kV 爪哇-巴厘输电网 · 候选变电站为 GI Sentul、GI Bogor Baru、GI Cibinong(距场地 5-15 公里)· 采用高压多点进线以实现 N+1 冗余 · 一期供电合同计划在 FID 前签定。

ESG & Green Financing Advantage ESG 与绿色融资优势

  • Green Financing Access: SLLs, green bonds, ECA cover, EPC supplier credit — lower cost of debt vs brown-power alternatives绿色融资渠道:可持续发展挂钩贷款、绿色债券、出口信贷机构承保、EPC 供应商信贷——相比化石电力方案,债务成本更低。
  • PLN GEAS / RECs: Immediately available RECs for 100% annual matching from Day-1PLN 绿电认购/绿证:绿证可即时获取,自投运首日起即可实现 100% 年度绿电匹配。
  • Hyperscaler Requirement: Microsoft, Google, Meta, ByteDance all have corporate net-zero pledges — green campus is a pre-condition for large leases云厂商的硬性要求:微软、谷歌、Meta、字节跳动均已作出企业净零承诺——绿色园区是拿下大额租约的前提条件。
  • Regulatory Direction: Indonesia NDC targets 23% renewable by 2025, 34% by 2030 — regulator tailwind, not headwind监管走向:印尼国家自主贡献目标为 2025 年可再生占比 23%、2030 年 34%——监管是助力而非阻力。
  • BDIC Blended Cost ~$0.072/kWh — 100% renewable annual matching achievable; clear 24/7 matching pathwayBDIC 综合成本约 0.072 美元/kWh——可实现 100% 年度绿电匹配,并有清晰的 7×24 小时全时匹配路径。

8. Technical Infrastructure — AI-Ready Day-1 技术架构

AI-native from Day-1. Future-proof to 2030+. Day-1 即为 AI 原生,面向 2030+ 前瞻设计。

Availability 可用性

  • Tier III+ / Hybrid Tier IV designTier III+ 级设计,局部按 Tier IV 混合标准
  • N+1 cooling, 2N power to rack冷却 N+1 冗余,机柜供电 2N 冗余
  • Multi-path HV grid intake高压电网多路径进线
  • >99.9999% availability target可用性目标高于 99.9999%

Cooling 冷却

  • Liquid-first D2C (Direct-to-Chip)以液冷为主的芯片直冷方案
  • Warm water 30-35°C supply / 40-45°C return温水循环:供水 30-35°C/回水 40-45°C
  • 60-75% heat capture Day-1; 85-90% future投运首日热量捕获率 60-75%,后续提升至 85-90%
  • 5-10 MW modular cooling pods, N+15-10 MW 模块化冷却单元,N+1 冗余
  • WUE < 0.2 L/kWh (world-class)水资源利用效率低于 0.2 L/kWh,达世界一流水平

AI Density AI 算力密度

  • 30-80 kW/rack base AI zones基础 AI 分区 30-80 kW/机柜
  • ≥120 kW/rack future provisioned预留未来 120 kW/机柜以上的扩展能力
  • NVIDIA DGX H100/H200/B200 certified已通过英伟达 DGX H100/H200/B200 认证
  • GB200 NVL72 (132 kW/rack) ready可承载 GB200 NVL72(132 kW/机柜)
  • 800V / HVDC-ready design pathway设计上预留 800V 高压直流升级路径

Efficiency 能效

  • Campus PUE: 1.15-1.20 at stabilised load园区 PUE:负载稳定后为 1.15-1.20
  • AI-zone PUE: ~1.10-1.12AI 分区 PUE:约 1.10-1.12
  • Inline with Google fleet PUE 1.09 benchmark与谷歌全球机群 1.09 的 PUE 基准处于同一水平
  • IEC 30134-2 certified measurement按 IEC 30134-2 标准进行认证计量

Connectivity 网络连接

  • Carrier-neutral PoP, dual metro fibre运营商中立接入点,双路城域光纤
  • Jakarta IX peering (2 independent providers)在雅加达 IX 对等互联(两家独立运营商)
  • Leased wavelengths to Telin / Telkom / Biznet SKKL租用 Telin/Telkom/Biznet 海缆系统波长
  • Optional CLS submarine cable participation可选择参与海缆登陆站建设

EPC Delivery EPC 交付

  • Chinese Tier-1 EPC; FIDIC Silver Book中国一线 EPC 总包,适用 FIDIC 银皮书
  • Fixed-price LSTK (~65-70% Phase 1 CAPEX)固定总价交钥匙合同(约占一期 CAPEX 的 65-70%)
  • Liquidated damages; performance guarantees设置误期违约金与履约保函
  • ~24-36 months Phase 1 delivery target一期交付目标约 24-36 个月

9. Anchor Client Strategy 锚定客户策略

Anchors commit first — capital follows. ByteDance as keystone; full tenant stack to 500 MW. 锚户先承诺,资本跟随。ByteDance 为基石,租户栈可支撑至 500 MW。

TIER 1 · ANCHOR第一梯队 · 锚定客户
ByteDanceStrategic rationale: Indonesia PDP localisation mandate + TikTok content moderation + AI inference for 280M Indonesian users字节跳动。战略理由:印尼 PDP 法的数据本地化强制要求 + TikTok 内容审核 + 面向 2.8 亿印尼用户的 AI 推理需求
30-80 MW → 150-250 MW
$110-130/kW/mo · 10+ yr BTS110-130 美元/kW/月 · 10 年以上定制建造租约
Tier 1B
Regional AI CloudAlibaba Cloud / AWS区域 AI 云厂商:阿里云/AWS
20-50 MW
$120-140/kW/mo
Tier 2
Indosat / Telkom Indonesia (Telkomsel)印尼电信运营商:Indosat/Telkom(Telkomsel)
10-30 MW each每家 10-30 MW
$100-120/kW/mo
Tier 2B
Govt / SOE (BUMN Digital)政府机构/国有企业(BUMN 数字板块)
10-40 MW
$95-115/kW/mo
Tier 3
Financial ServicesBCA, Mandiri, BRI金融机构:中亚银行、曼迪利银行、印尼人民银行
5-20 MW
$105-125/kW/mo
Tier 4
Industrial AIManufacturing, E-Commerce工业 AI:制造业与电商
10-30 MW
$100-120/kW/mo
Tier 5
Singapore OverflowDC-constrained tenants新加坡外溢需求:受当地机房容量限制的租户
20-60 MW
$115-135/kW/mo

10. Connectivity — Carrier-Neutral, Metro-First 网络连接

Metro & Domestic 城域与国内

  • 2 × independent metro fibre providers to Jakarta IX两家独立城域光纤运营商接入雅加达交换中心
  • Dual Points of Presence (PoPs) on campus园区内设双接入点(PoP)
  • Jakarta IX peering: diverse entry/exit routing在雅加达 IX 对等互联,进出路由多样化
  • Dark fibre to Equinix JK1/JK2 for cloud on-ramps裸光纤直连 Equinix JK1/JK2,打通云入口
  • Carrier-neutral design: no vendor lock-in运营商中立架构,不被单一供应商锁定

International Subsea 国际海缆

  • Leased wavelengths via Telin/Telkom SKKL systems通过 Telin/Telkom 海缆系统租用波长资源
  • Access to Biznet (BDI-1), Moratel (IM-1) SEA cables可接入 Biznet(BDI-1)与 Moratel(IM-1)东南亚海缆
  • Strategic upside: optional CLS (Common Landing Station) participation战略增量:可选择参与共用海缆登陆站(CLS)建设
  • Singapore-Jakarta latency ~12-15 ms (campus target)新加坡至雅加达时延约 12-15 毫秒(园区目标值)
  • Dual-path international redundancy built in国际链路内置双路径冗余

Cloud Connectivity 云连接

  • AWS Direct Connect, Azure ExpressRoute, Google Cloud Interconnect via Jakarta IX经雅加达 IX 接入 AWS Direct Connect、Azure ExpressRoute、Google Cloud Interconnect
  • Alibaba Cloud Express Connect (critical for ByteDance ecosystem)阿里云高速通道(对字节跳动生态至关重要)
  • Telkom IndiCloud and Indosat DX peering on-siteTelkom IndiCloud 与 Indosat DX 在园区内实现对等互联
  • Carrier-neutral IX fabric: BGP route diversity运营商中立的交换架构,BGP 路由多样化
  • Latency to Singapore <20 ms; HK <50 ms; Tokyo <70 ms至新加坡时延低于 20 毫秒,至香港低于 50 毫秒,至东京低于 70 毫秒
Connectivity Strategy Principle: BDIC is a carrier-neutral wholesale campus — no long-term exclusivity with any single connectivity provider. Tenants can bring their own circuits, buy bundled services from BDIC, or connect through any PoP-resident carrier. This maximises tenant flexibility and supports premium lease pricing. 网络策略原则:BDIC 是一个运营商中立的批发型园区,不与任何单一网络供应商签订长期独家协议。租户可自带线路、从 BDIC 采购打包服务,或通过任一入驻园区 PoP 的运营商接入。这既最大化了租户的灵活性,也为溢价租金提供了支撑。

11. Financial Overview 财务概览

Infrastructure-grade returns. Hyperscaler-grade lease security. 基础设施级回报,超大规模客户级租约保障。

Phase 1 CAPEX Breakdown (USD 820-900M) 一期 CAPEX 拆解

Component科目%USD M
Data Hall Civil + Structure数据机房土建 + 结构25-28%~210-250
EPC (Power + Cooling systems)EPC(电力 + 冷却系统)30-34%~245-300
BESS (30 MW / 160 MWh)储能电池系统6-8%~50-70
Grid Interconnection & HV并网与高压设施5-7%~42-60
Connectivity + PoP网络连接 + PoP2-3%~18-25
EPCM, Soft costs, ContingencyEPCM、软成本、备用金10-12%~85-110
Land (injected as equity)土地(作股权注入)8-10%~70-90

Return Metrics 回报指标

Revenue (100 MW @ 85% util)
收入(100MW 85% 利用)
$112-142M/yr
EBITDA Margin
EBITDA 利润率
55-65%
Project IRR (Equity)
项目 IRR(股权)
15-22%
MOIC (5-7 yr hold)
投资倍数(持有 5-7 年)
2.0-3.2×
DSCR (Senior Debt)
优先债偿债覆盖倍数
>1.35×
CIT Holiday (PMK 69/2024)
企业所得税假期
Up to 20 yr
Breakeven Utilisation
保本利用率
~55%
Phase 1 CAPEX Intensity
一期单位造价
$7.5-8.5M/MW

Revenue assumes $110-140/kW/month BTS lease rate. IRR pre-tax, unlevered project basis. All figures illustrative; subject to final underwriting. 收入按 110-140 美元/kW/月的定制建造租金测算。IRR 为税前、无杠杆的项目层面口径。所有数据仅供示意,最终以承做审核结果为准。

12. Capital Structure — Phase 1 (USD 820-900M) 资本结构 · 一期

Senior Debt (60-65%) 优先债(60-65%)

  • Target: USD 535-585M at closing目标规模:交割时 5.35-5.85 亿美元
  • Tenor: 12-15 year term loan期限:12-15 年定期贷款
  • Providers: DFIs (IFC, ADB, AIIB), regional bank clubs出资方:开发性金融机构(IFC、ADB、AIIB)及区域银团
  • ECA cover from EPC suppliers (Sinosure, K-Sure)由 EPC 供应商方安排出口信贷机构承保(中信保、韩国出口保险)
  • Security: land, leases, PPAs, project cash flows担保物:土地、租约、购电协议及项目现金流
  • DSCR covenant: >1.35× (base case 1.55×)偿债覆盖率契约:高于 1.35 倍(基准情形 1.55 倍)

Equity (30-35%) 股权(30-35%)

  • Target: USD 285-315M at FID目标规模:FID 时 2.85-3.15 亿美元
  • Land injected as sponsor equity at appraised value土地按评估价值作为发起人股权注入
  • Equity investors: infra funds, sovereign wealth, family offices股权投资人:基础设施基金、主权财富基金、家族办公室
  • HoldCo (SG/HK) for investor aggregation + exit optionality设新加坡/香港控股公司,用于归集投资人并保留退出灵活性
  • Sell-down / REIT exit post-stabilisation资产稳定运营后通过减持或 REIT 退出
  • Minimum 25% co-invest from development sponsor开发方发起人须跟投不低于 25%

Green / Alternative Financing 绿色融资与替代融资渠道

  • SLLs and green bonds for BESS and PPA assets针对储能与购电协议资产发行可持续发展挂钩贷款及绿色债券
  • Supplier credit from Chinese EPC (CRCC, PowerChina)由中方 EPC(中国铁建、中国电建)提供供应商信贷
  • Government facilitation: PLN take-or-pay guarantees政府层面协调:PLN 提供照付不议担保
  • Potential BUMN co-investment (Telkom, PLN Nusantara)印尼国企潜在跟投(Telkom、PLN Nusantara)
  • Tax Holiday reduces effective cost of equity by 3-5%税收免税期可将实际股权成本压低 3-5 个百分点
  • Stage-gate drawdowns match construction milestones按建设里程碑分阶段提款,资金与工程节点匹配

13. Competitive Positioning 竞争定位

BDIC is the only power-secured, AI-ready, renewable-led hyperscale campus available at scale in Indonesia. BDIC 是印尼唯一一个规模级、电力已锁、AI 就绪、可再生能源主导的超大规模园区。

Dimension维度BDIC (Bogor)SingaporeJohor (MY)Jakarta (Peers)Ashburn (USA)
Power Availability电力可用性✓ Secured已落实✗ Gate-queued需排队申请✓ Available有富余△ Constrained偏紧✗ Severe queue排队严重
Renewable % Day-1投运首日可再生占比>80% PPA购电协议锁定 80% 以上~30-50%~50% (YTL solar)约 50%(YTL 光伏)~20-40%~50% procured约 50%(采购绿电)
AI Density (kW/rack)AI 机柜功率密度30-120 kW30-80 kW30-80+ kW20-60 kW30-80+ kW
Data Loc. Mandate数据本地化强制要求✓ PDP Law受 PDP 法约束✓ PDP Law受 PDP 法约束
CAPEX Intensity/MW单位造价(每 MW)$7.5-8.5M$12-16M$8-11M$7-10M$10-14M
Tax Incentive税收激励20yr CIT Holiday20 年所得税免税期Pioneer Status先锋产业地位CIT Holiday所得税免税期IRA credits《通胀削减法案》税收抵免
Land Availability土地可获得性181 ha secured181 公顷已锁定Moratorium暂停审批Active; limited在售但有限Urban; complex城区地块,手续复杂Scarce稀缺
Scale Potential规模上限≤500 MW>100 MW: rare超 100 MW 者罕见≤500 MW (YTL)最高 500 MW(YTL)≤200 MWGW-scale marketGW 级市场

✓ = structural advantage · △ = neutral/improving · ✗ = structural constraint ✓ = 结构性优势 · △ = 中性/正在改善 · ✗ = 结构性制约

14. Government Incentives & Regulatory Pathway 政策与监管路径

Fiscal & Non-Fiscal Incentives 财政与非财政激励

Corporate Income Tax Holiday企业所得税免税期PMK 69/2024 (amending PMK 130/2020) — up to 20 years CIT exemption; eligible as 'pioneering industry' (digital infrastructure)依据 PMK 69/2024 号法规(对 PMK 130/2020 的修订),最长可享 20 年企业所得税免征;数字基础设施可按"先导产业"申请认定。
Import Duty & VAT Facilities关税与增值税优惠Customs exemption on critical data centre equipment; PLN-supplied power exempt from sector VAT in certain structures数据中心关键设备可免征关税;在特定架构下,PLN 供电可免征行业增值税。
OSS-RBA Fast-TrackOSS-RBA 快速审批通道Online Single Submission — risk-based streamlined licensing; BKPM Investment Board priority facilitation线上一站式提交系统——基于风险分级的简化许可流程;由投资协调委员会(BKPM)提供优先协调支持。
Joint Facilitation Team (JFT)政府联合协调小组Cross-ministry task force guaranteeing SLA response times on regulatory milestones; President-level mandate for strategic projects跨部委专班,对各审批里程碑承诺服务响应时限;战略项目享有总统级授权支持。
PLN GEAS / RECsPLN 绿电认购与绿证Immediately available Green Energy Approval System certificates for 100% annual renewable matching from Day-1绿色能源认证可即时获取,自投运首日起即可实现 100% 的年度绿电匹配。
KEK Nongsa PlaybookKEK Nongsa 成熟经验Batam KEK Nongsa Digital Park precedent: full fiscal zone + connectivity + regulatory streamlining — replicable model for BDIC巴淡岛 KEK Nongsa 数字园区先例:完整财税特区 + 网络资源 + 审批简化——这一模式可被 BDIC 直接复制。

Regulatory Pathway (6 Steps) 监管路径 6 步

Step 1
SPV Incorporation + NIB设立项目公司并取得营业识别号
PT BDIC registered; NIB via OSS-RBA完成 PT BDIC 注册,通过 OSS-RBA 取得 NIB
Step 2
KKPR Land Conformity取得 KKPR 用地符合性许可
Spatial planning approval from ATR/BPN由国土空间规划部/国土局出具空间规划批复
Step 3
AMDAL / UKL-UPL环境影响评价
Environmental impact assessment (6-9 mo)环评办理周期 6-9 个月
Step 4
PBG + SLF建设许可与使用许可
Building permit + occupancy certificate建筑施工许可证 + 竣工使用合格证
Step 5
PLN Grid Agreement签署 PLN 供电协议
Surat Ketersediaan Daya + interconnection取得电力可用性确认函并完成并网
Step 6
PSE + PDP Registration电子系统运营商与数据保护备案
Electronic System Provider (Kominfo) + PDP向通信信息部办理 PSE 登记,并完成 PDP 备案

15. SPV & Legal Structure SPV 与法律架构

Clean risk allocation, bankable security package, tax-holiday compatible, lender-aligned governance. 清晰的风险分配,可银团化担保包,兼容税假,与贷款人对齐的治理架构。

BDIC Holdings Pte. Ltd.
HoldCo (Singapore or HK) · Equity aggregation, exits控股公司(新加坡或香港)· 归集股权、承载退出
PT BDIC — Project SPV
The bankable "single point of truth" · Land + all material contracts + project financing + signatory authority可融资主体的"唯一权威载体"· 集中持有土地、全部重大合同、项目融资及签署权限
PT BDIC O&M
Operations运营维护
PT BDIC Power
BESS Assets储能资产
PT BDIC Connect
IRUs / Fibre光纤资源与使用权
PT BDIC Property
Non-core RE非核心不动产

Key Documents & Signatory Matrix 关键文件与签署矩阵

Document文件Counterparty签约主体Required Signatory须签署人
Land Acquisition (HGB/HPL)土地取得(HGB/HPL 权证)BDIC SPVBDIC 项目公司President Director + Board总裁 + 董事会
EPC Contract (FIDIC Silver)EPC 总包合同(FIDIC 银皮书)BDIC SPVBDIC 项目公司President Director + CFO (dual-sign)总裁 + 财务总监(双签)
PLN / Utility AgreementsPLN 及公用事业协议BDIC SPVBDIC 项目公司President Director总裁
Renewable PPAs可再生能源购电协议BDIC SPVBDIC 项目公司President Director + CFO (dual-sign)总裁 + 财务总监(双签)

16. Risk Analysis & Mitigants 风险与缓释

Risk风险Impact影响Prob概率Mitigation缓释
PLN Grid DelayPLN 电网延误HighMediumMulti-point HV intake; BESS bridge; pre-FID grid confirmation covenant in lending docs高压多点进线;以储能作过渡衔接;在融资文件中设置 FID 前必须取得电网确认函的先决条件。
Anchor Tenant Walkaway锚定客户退出HighLowLOI/HOA structure with termination fees; target secondary anchors (Alibaba, Google, AWS) in parallel采用带违约金条款的 LOI/HOA 结构;同步接洽备选锚户(阿里、谷歌、AWS)。
EPC Cost OverrunEPC 造价超支MediumLowFixed-price LSTK contract; LDs; 10-12% contingency; FIDIC Silver Book; Chinese Tier-1 EPC track record采用固定总价交钥匙合同;设置误期违约金;预留 10-12% 备用金;适用 FIDIC 银皮书;选用有业绩的中国一线 EPC。
Renewable PPA Delay可再生能源 PPA 延迟MediumLowPLN RECs available Day-1 as bridge; geothermal (existing licenses) near-immediate; staggered PPA closing投运首日即可用 PLN 绿证过渡;地热依托现有许可可近乎即时供电;PPA 分批错峰签约。
Regulatory / Permitting监管与许可MediumMediumJFT fast-track; OSS-RBA risk-based; AMDAL started early; KEK Nongsa precedent de-risks pathway依托政府联合协调小组走快速通道;OSS-RBA 按风险分级审批;提前启动环评;KEK Nongsa 先例已验证路径可行。
FX (IDR/USD)汇率(印尼盾/美元)MediumMediumLeases denominated in USD; debt in USD/SGD; BESS and civil costs partially hedged in IDR (local cost base)租约以美元计价;债务以美元/新元计价;储能与土建成本以印尼盾本地成本部分对冲。
Seismic / Natural Hazard地震与自然灾害MediumLowSNI 1726 seismic design; Bogor inland elevation avoids Jakarta subsidence; IFC EHS standards按 SNI 1726 规范进行抗震设计;茂物内陆高地完全规避雅加达地面沉降风险;遵循 IFC 环境健康安全标准。
Geopolitical (ByteDance)地缘政治(字节跳动)Low-Med中低LowTenant stack designed to not exceed 35% single-tenant concentration; sovereign / BUMN tenants as anchors of last resort客户结构设计上确保单一客户集中度不超过 35%;主权机构/印尼国企作为最后的兜底锚户。

17. Development Milestones & Critical Path 开发里程碑与关键路径

Anchors commit → Capital follows → Construction → Energisation 锚户承诺 → 资本跟随 → 建设 → 投运

Phase 0
Month 0-1
  • Strategic readiness confirmed战略准备度确认完成
  • LOI/HOA with ByteDance与字节跳动签署 LOI/HOA
  • SPV formed (PT BDIC)项目公司 PT BDIC 设立完成
  • JFT engagement initiated启动与政府联合协调小组的对接
Phase 1A
Month 1-4
  • Land into SPV + HGB title土地注入项目公司并取得 HGB 权证
  • Renewable PPA term sheets签署可再生能源 PPA 条款清单
  • PLN grid feasibility confirmedPLN 电网可行性获得确认
  • EPC shortlist + FIDIC draft确定 EPC 短名单并起草 FIDIC 合同
Phase 1B
Month 4-8
  • AMDAL submission提交 AMDAL 环评申请
  • KKPR approval取得 KKPR 用地符合性批复
  • Lender mandate letters取得贷款方授权函
  • EPC fixed-price agreedEPC 固定总价谈定
FID
Month 8-12
  • Anchor lease signed锚定客户租约正式签署
  • Debt documentation closed债务融资文件全部落定
  • EPC contract executedEPC 合同正式签订
  • Land injected as equity土地作为股权注入
Construction
Month 12-36
  • HV grid + BESS civil work高压电网与储能配套土建施工
  • Data hall structure + MEP机房主体结构与机电安装
  • Cooling system install冷却系统安装
  • Connectivity PoP build网络接入点建设
COD Ph.1
Month 30-36
  • Phase 1 energisation (100 MW)一期 100 MW 通电投运
  • Tenant fit-out + commissioning租户装修入驻与系统调试
  • Tier III+ certification取得 Tier III+ 等级认证
  • Phase 2 planning starts二期规划启动

18. Why Invest Now — Five Reasons This Window Will Close 投资时机 · 五个窗口即将关闭的理由

1

ByteDance LOI Window Is Now 字节跳动的签约窗口就在当下

Anchor commitment is the gating item — capital follows contracts. ByteDance is actively evaluating SEA capacity now; a 6-month delay risks losing the anchor to Johor or Bangkok competitors. 锚定客户的承诺是整个项目的关键闸口——资本永远跟着合同走。字节跳动当前正在积极评估东南亚的容量布局;一旦延误 6 个月,锚户很可能被柔佛或曼谷的竞争者抢走。

2

Land Is Already Secured 土地已经落定

181 ha in a single parcel is extremely rare at this scale in Java. The site is pre-screened for HV access, seismic compliance, and water sourcing. Replicating this takes 3-5 years. 在爪哇岛,能有 181 公顷的单一连片地块极为罕见。该场地已就高压接入、抗震合规、水源保障完成前期筛查。要重新复制这样一块地,需要 3-5 年。

3

Power Queue Before It Forms 抢在电力排队形成之前

Indonesia's hyperscale market is 2-3 years behind Singapore's bottleneck. Locking in PLN grid capacity and renewable PPAs now — before the queue — is a durable 10-year cost advantage. 印尼超大规模市场比新加坡的电力瓶颈晚 2-3 年到来。现在——在排队机制尚未形成之前——锁定 PLN 电网容量和可再生能源购电协议,可换来长达十年的持续成本优势。

4

Tax Holiday at Peak Value 税收优惠正处价值高点

PMK 69/2024 CIT holiday is available but oversubscribed; BDIC qualifies as pioneering industry. The 20-year holiday represents a USD 200-400M NPV benefit vs a conventional investment. PMK 69/2024 号法规下的所得税免税期目前仍可申请,但申请量已远超配额;BDIC 符合"先导产业"认定条件。相较常规投资,这 20 年免税期的净现值收益达 2-4 亿美元。

5

First-Mover AI Infrastructure Premium AI 基础设施的先发溢价

SEA's first 500 MW AI-native campus in Indonesia commands 20-30% lease premium over followers. Once ByteDance, AWS, and Alibaba are signed, the moat is effectively unassailable. 作为东南亚首个落地印尼的 500 MW AI 原生园区,其租金可较后来者高出 20-30%。一旦字节跳动、AWS 和阿里相继签约,这条护城河基本无从撼动。

Bogor Digital Infrastructure Complex · Project Overview
Content sourced from: UHR BDIC Investor Deck 2026 · December 2025 · Dr. Ulf Henning Richter
印尼茂物数字基础设施综合体 · 项目介绍 · 内容来源:UHR BDIC 投资材料 2026(2025 年 12 月,Ulf Henning Richter 博士)
Companion documents: Project Analysis · DD Question List · Financial Model (.xlsx)